ITK/Release 4/Modularization/Transition Plan: Difference between revisions
From KitwarePublic
< ITK | Release 4 | Modularization
Jump to navigationJump to search
Line 5: | Line 5: | ||
* The target date for transforming the repository is '''Friday March 4th 2011''' | * The target date for transforming the repository is '''Friday March 4th 2011''' | ||
* The repository should be reopen for normal activity by '''Tuesday March 8th 2011''' | * The repository should be reopen for normal activity by '''Tuesday March 8th 2011''' | ||
= Git Repository Conversion = | |||
= Detailed Plan = | = Detailed Plan = |
Revision as of 21:24, 18 February 2011
This page describes the plan for transforming the current Monolithic ITK repository into a Modularized one.
Major Dates
- The target date for transforming the repository is Friday March 4th 2011
- The repository should be reopen for normal activity by Tuesday March 8th 2011
Git Repository Conversion
Detailed Plan
Date | Major Event | What will be done | Who will do it |
---|---|---|---|
March 1st Tuesday | Freezing Git Repository | Write Access will be disabled | Brad King |
March 4th Friday | Full Conversion | A single large Git commit that will move all the files to their final destination | Brad King |